PUWER
PUWER inspection software for work equipment.
Run regulation 6 inspections from the machine's QR label, record the interval you chose and why, and produce the PUWER inspection record against the machine with its next-due date. For in-house maintenance teams and the competent persons who inspect for them. On every plan, including the 30-day free trial.
What PUWER regulation 6 asks for
Regulation 6 of the Provision and Use of Work Equipment Regulations 1998 in brief. The duties and the occasions are the regulation’s own; Hovermarks changes where the record lives and whether it is tied to the machine that was inspected, not what the law requires.
After installation, before first use
Regulation 6(1)(a). Where safety depends on how the equipment is installed: confirm it is installed correctly and safe to operate.
After assembly at a new site or location
Regulation 6(1)(b). The same check after the equipment is reassembled somewhere new.
At suitable intervals
Regulation 6(2)(a). Where it is exposed to conditions causing deterioration liable to result in danger, so the deterioration is found and put right in good time.
After exceptional circumstances
Regulation 6(2)(b). Each time something happens that could jeopardise its safety, such as a major modification, repair, known damage or a long period out of use.
Record the result
Regulation 6(3). The result is recorded and kept until the next inspection under regulation 6 is recorded. There is no prescribed form.
Equipment that leaves or arrives
Regulation 6(4). Equipment used in another undertaking, or obtained from one, must be accompanied by physical evidence that the last inspection was carried out.
HSE’s test is significant risk: an inspection is needed where faulty installation, deterioration or an exceptional event could lead to a failure that causes a major injury. Lifting equipment is thoroughly examined under LOLER instead, and ladders are inspected under the Work at Height Regulations 2005. The PUWER inspection checklist goes through what to check and what to record, with a free printable version.
What you get
A PUWER template built from regulation 6
The built-in "PUWER Inspection - Work Equipment (Reg 6)" checklist asks for the reason for the inspection (after installation or assembly at a new site, periodic, after exceptional circumstances, or after repair or modification) and the interval applied with the risk basis for choosing it. It then covers guards and protective devices, interlocks and trips, the emergency stop, isolation and lock-off, controls and unexpected start-up, markings and warnings, electrical enclosures and cables, mechanical condition, stability, leaks, and access and lighting, and ends with whether the equipment is safe to continue in use, the remedial action and its date, the next inspection due and the competent person. Use it as it is or copy and edit it for a type of machine. A separate template covers profile beds.
Every plan.
The PUWER inspection record
The Statutory report button on the inspection produces the PUWER inspection record, with the report number and page numbers. It says "inspection" throughout and cites only regulation 6, because PUWER prescribes no report contents. Before issue Hovermarks checks that the record names the organisation, where the inspection took place, the equipment and its serial number or mark, the competent person, whether the equipment is safe to continue in use, and when the next inspection is due, and tells you what is missing.
Every plan, including the trial, when the organisation's Regulations setting is UK.
Your interval, machine by machine
Each machine, or each category of machine, gets a schedule on the interval you chose from your risk assessment. When the next inspection due date on a record is earlier than the schedule's date, it becomes the machine's next-due date, so the QR scan page, the reminder emails and the overdue counts never show a later date than the record.
Schedules, overdue alerts and email reminders are on every plan.
Defects that reach the person fixing them
A failing answer on a question marked to raise a flag (the guard, interlock, emergency stop and isolation checks are marked in the template) opens a defect and a corrective action against the machine. Set a severity and a remedy date, raise a work order with parts and labour, and set the machine out of service until the work is done.
Defects and work orders on every plan. Automation rules that raise work orders from failed inspections: Professional.
Pre-use checks on the same record
An operator's pre-use check is not a regulation 6 inspection and does not need recording, but many teams keep one anyway. Pre-shift check templates with photo capture run from the same QR label, so the machine's record shows both, and a fault reported between inspections lands on the right machine.
Every plan.
Equipment that moves
Move a machine between sites and its history goes with it. HSE's guidance (L22, paragraph 105) says that for smaller items a tag, colour code or label can show the last inspection was done, as long as it links back to the record. With the public status panel switched on, a scan of the Hovermarks label shows when the item was last inspected and when it is next due, without a login.
Every plan. The public status panel is off until an Admin turns it on.
Use case
A workshop moving its PUWER register off paper
A maintenance lead imports the machine list from a CSV file, prints a QR label for each machine and sets a schedule per category, writing down the interval and why it suits the equipment. On the day, the competent person scans the label, taps Start inspection, works through the checklist with photos, and downloads the PUWER inspection record. A failed guard check opens a defect against that machine with a remedy date, the machine is set out of service, and the next inspection due on the record drives the next reminder. When an HSE inspector or an insurer asks how a machine is inspected, the answer is its record: the interval and the reason, every inspection, every defect and when it was put right.
What it does not do
- It does not set your inspection intervals. The interval comes from your risk assessment and the manufacturer’s instructions.
- It does not make anyone compliant. It keeps the record; deciding what the inspection covers, and the competence of the person who carries it out, stay with you.
- It does not treat lifting equipment as PUWER equipment: hoists, slings and other lifting equipment get a LOLER thorough examination, covered on the LOLER inspection software page.
- It needs a data connection to open, load machines and start an inspection. If the signal drops part-way through, the answers are held on the device and sent when it returns, while the app stays open.
Frequently asked questions
- Which plan includes the PUWER inspection record?
- Every plan, including the 30-day free trial, when your organisation's Regulations setting is UK. The LOLER report of thorough examination and the PSSR report of examination are on every plan in the same way. Professional adds automation rules, audit log search, the certificate register and, for organisations that joined from 25 November 2026, the auditor pack and scheduled email reports.
- How often do PUWER inspections need to be done?
- PUWER sets no fixed interval. Regulation 6(2) requires equipment exposed to conditions causing deterioration that could lead to dangerous situations to be inspected at suitable intervals and after exceptional circumstances. HSE's guidance (L22, paragraph 100) says the frequency should depend on how quickly the equipment is likely to deteriorate, taking account of its type, how it is used and the conditions it is exposed to. Hovermarks records the interval you choose and the reason; it does not choose it for you.
- Who can carry out a PUWER inspection?
- A competent person. Regulation 2 defines an inspection as a visual or more rigorous inspection by a competent person. HSE's guidance says an in-house employee with adequate knowledge of the equipment can often carry it out, but whoever decides what the inspection covers needs enough knowledge and experience to decide what to check, how and when. An outside inspector can be invited with the Contractor role and record inspections in your account.
- Is a pre-use check a PUWER inspection?
- No. HSE's guidance (L22, paragraph 81) says that for regulation 6, inspection does not include an operator's pre-use check, and that while inspections need to be recorded, pre-use checks do not.
- Does PUWER regulation 6 apply to lifting equipment and ladders?
- No. Regulation 6(5) excludes work equipment for lifting loads including persons, which is thoroughly examined under LOLER instead, and equipment covered by regulation 12 of the Work at Height Regulations 2005, such as ladders, which has its own inspection duty. Hovermarks holds all three on the same register, each with its own checklist and interval.
- How much does PUWER inspection software cost?
- Starter is £15 per user per month and Professional £29, or £12 and £23 a month billed annually. No VAT is added: BrainBoxIT Limited is not registered for VAT. There are no per-inspection or per-report fees, and the 30-day free trial needs no card.
Contains public sector information licensed under the Open Government Licence v3.0. Quotations from legislation and HSE guidance are Crown copyright. Hovermarks is not endorsed by HSE or any other public body.
Stop chasing paperwork.
Start proving compliance.
Tag your first asset, run your first inspection, and export an auditor pack, all on your free 30-day trial. No credit card required.